Growing data centre demand is creating a new opportunity to fund recycled water infrastructure. In western Sydney, coNEXA’s $250 million AquaNet expansion will supply NEXTDC’s S4 Sydney data facility, while establishing infrastructure that could support other industrial and community use over time.
Fully funded by the private sector, the project will supply up to 16 million litres of recycled water a day from coNEXA’s AquaNet Fairfield plant to the Horsley Park data centre. It has approval from the Independent Pricing and Regulatory Tribunal (IPART), with first water expected in late 2027.
For coNEXA CEO Kurt Dahl, the significance extends beyond a single connection. Data centres bring a combination of material demand, commercial capacity and urgency that has historically been difficult to secure for recycled water.
“The demand from data centres is a once-in-a-hundred year opportunity for recycled water in Australia," he said.
"From an energy efficiency perspective, data centres prefer water-based cooling over energy-based cooling. They don’t want to use drinking water, however, for them to commit to recycled water we need to provide them with commercial and timely solutions – our AquaNet expansion is a perfect example of this.”
The project reflects priorities AWA has advanced through three recent submissions on data centres and AI infrastructure, including its October submission to the Australian Government’s consultation on Getting it right: Building AI infrastructure that works for Australia.
The submission calls for recycled water to meet long-term data centre water demand, with proponents funding the infrastructure and supply solutions required, protecting residential customers from additional costs. It also advocates enforceable water and energy efficiency targets, transparent volumetric water reporting, and integrated planning that addresses urban heat and water–energy–carbon trade-offs.
For Dahl, who has worked in recycled water for 25 years, data centre demand could help overcome longstanding barriers to investment.
“It's hard to get all of the things to line up to get a recycled water project off the ground," he said.
"Historically, it's because we have a highly variable climate. Recycled water is always popular when it's dry, and then when it starts to rain, many people lose interest in recycled water.”
The difference now is the pace at which prospective customers need infrastructure delivered, Dahl said.
“Data centres require a sense of speed and urgency that I've not seen before in the water sector. There is a great opportunity for recycled water right now, all we need to do is move fast and we could do some great things for recycled water in Australia," he said.
S4 Sydney is designed to provide up to 365 megawatts of IT capacity. At full IT load, its designed Power Usage Effectiveness (PUE) is 1.125, a direct result of using water-based cooling. This PUE is more than 25% below the 2026 global average, according to the Uptime Institute.
Dahl said assessing cooling choices requires consideration of both water and power availability, with solutions suited to local conditions.
“Ultimately, Australia must pursue and support the data centres that represent global best-practice in terms of sustainability. That is always going to be a balance between understanding how much water you might have, ideally recycled water, versus how much power is available, and how you drive the best outcome in terms of value creation and resource efficiency," he said.
For developers, cooling decisions also affect the power available for computing.
“Data centres make money from turning electricity into compute. If electricity supply is limited and recycled water is available, the preferred approach to cooling is straight forward," he said.
That balance is central to AWA’s advocacy, which calls for water security, energy demand, and emissions to be assessed together when determining sustainable long-term outcomes.
The AquaNet expansion could reuse up to 5.8 billion litres annually that would otherwise be released to the ocean, taking the wastewater equivalent of up to 35,000 homes out of a constrained sewerage network.
Its wider potential lies in the recycled water treatment and transmission capacity established to serve the data centre. Dahl said other users could access spare capacity outside peak cooling periods.
“Data centres don't operate continuously at peak water consumption. While they need to have the peak secured, for the balance of the year there's spare capacity in that system to provide other users," he said.
Customers along the pipeline route could potentially replace a substantial share of their drinking water use, while retaining drinking water access when recycled supplies were needed by the data centres for peak cooling demand.
“For these off-peak customers, we can’t guarantee that they are going to come off drinking water altogether, but we might be able to meet 90% of their annual water demands with recycled water," he said.
"A 90% reduction in drinking water use for an existing customer is a great outcome for the customer and the broader community.”
These figures illustrate a possible servicing arrangement, focused on maximising recycled water demand. Additional potential uses include other industrial use, and irrigation of public open spaces, supporting urban greening and cooling.
“These new pipes will last 70+ years and provide a service to areas which have never had recycled water before. The current commercial support of data centres enables the creation of long-lasting infrastructure," Dahl said.
"Data centres may continue to use recycled water in 20 or 30 years' time, that's fine, but there's a chance they won’t. The infrastructure can then be available for other end uses. Either way, the community benefits.”
Securing those opportunities requires early engagement. Dahl said data centres need certainty about water supply before committing to cooling designs, with consequences for both technology selection and investment location.
“But the data centres ultimately have a choice when it comes to cooling. They don't need to use water," Dahl said.
“Once they've made that decision, those design and construction decisions are largely one-way doors. It is difficult, if not impossible, to change this decision in the future.”
For coNEXA, that means matching investment and delivery to customers' requirements.
“As an active investor in water infrastructure, coNEXA will take on some of the commercial risks that the data centres want us to take on. We will deliver it at the speed that the data centres need and give them certainty that we're going to do that," he said.
For Dahl, the critical challenge is to secure recycled water investment while developers are still deciding how their facilities will operate.
“The preferred approach to cooling is determined early in the design phase of a data centre. These opportunities need to be intercepted at this point and be provided with sufficient investment certainty for recycled water to be included," he said.